The steel frame of the hall from inside during erection: rows of columns and roof beams along its whole length

ProjectAll projects

Sa-Ba

Krepost, Dimitrovgrad

gross floor area
2,900 m²
steel structure
160 t
Stage
Completed
gross floor area
2,900 m²
steel structure
160 t
Stage
Completed

A steel-⁠framed hall for automotive production, with all its building services. Horizont-⁠Ivanov was the general contractor, on a full engineering basis.

A steel-⁠framed hall in Krepost for automotive production. Horizont-⁠Ivanov was the general contractor, on a full engineering basis.

  • Steel structure
  • Built-⁠up roof: LT profiled sheeting, mineral wool and membrane
  • Facades of mineral wool panels
  • Building services: electrical, plumbing, HVAC and fire suppression
  • Polished industrial concrete floor
  • Water tank
Sheet 1/1Key plan02550 km

174 km from our plant in Pleven, in a straight line.

water tank
450 m³
  1. Investment: by the client
  2. Design: by us
  3. Permits: by us
  4. Fabrication: by us
  5. Construction: by us
  6. Maintenance: by us
Sa-Ba: fig. 1 of 8
Fig. 1
Sa-Ba: fig. 2 of 8
Fig. 2
Sa-Ba: fig. 3 of 8
Fig. 3
Sa-Ba: fig. 4 of 8
Fig. 4
Sa-Ba: fig. 5 of 8
Fig. 5
Sa-Ba: fig. 6 of 8
Fig. 6
Sa-Ba: fig. 7 of 8
Fig. 7
Sa-Ba: fig. 8 of 8
Fig. 8

Enquire about a similar building

Like Sa-⁠Ba: 2,900 m² gross floor area, 160 t steel structure.